Kier Construction has started work on a £19m school project expected to rank as the largest structure in the UK built with the latest cross-laminated timber (CLT) technology. Foundations are now being laid for the William Perkin Church of England High School in Oldfield Lane North, Greenford, under a fast-track programme that will see the first pupils enter the new building at the start of term next September.
William Perkin High is the latest in a succession of challenging, high-speed school projects Kier has undertaken using CLT, including the Sir Alec Reed Academy in nearby Northolt, completed last summer.
The team is on course for the first section hand over for the Year 7 intake in September 2013 - some 10 months after Kier moved onto the former Glaxo sports and social club grounds to begin demolition of the old premises and site preparations.
The design & build contract has been awarded to Kier's Maple Cross office by Ealing Council on behalf of the Twyford Academies Trust, which will run the school.
The new school will have places for 1,200 11 to 16-year-olds, plus a sixth form with places for 250 students and a centre for children with special educational needs. The local community will also be able to use the schools facilities, which include five sports pitches, floodlit hard playing surfaces, indoor sports hall and activity studio.
Following the first intake of pupils next September, internal fit-out works will continue until April 2014.
Kier Construction operations director Norman Elliott said: "We're off to a flying start. Having only taken possession of the site in October, the old buildings have been demolished and piling has been completed. Now the foundations are being laid, the project is really starting to come out of the ground. We are geared up for a fast construction programme in order to hand over to the school next August."
CLT construction technology has been chosen because it offers efficient, high-speed installation using modular factory-made precision components that can be delivered to site and rapidly erected. It has proved less weather-dependent and more sustainable than conventional construction methods.
CLT specialist KLH UK is manufacturing some 3,800cu m of timber panels, amounting to more than 1,700 tonnes and covering combined floor and wall areas totalling approximately 22,500sq m. The panels will start arriving at Greenford in the New Year and the site installation programme is expected to be 16 to 18 weeks, allowing the various follow-on trades to complete their work under the tight timescale.
To mark the laying of foundations, a special ceremony was held on site last week attended by local MP Stephen Pound, senior council figures, community leaders and selected local primary school pupils. They joined a service of blessing led by the Bishop of Willesden, the Rt Rev. Pete Broadbent.
For more information visit: www.kier.co.uk